Proponent: Level Crossing Removal Authority (LXRA)

The Edithvale and Bonbeach level crossing removals are proposed under the Victorian Government’s program of 50 level crossing removals. The removal of these two separate level crossings at Edithvale Road, Edithvale and Station Street/Bondi Road, Bonbeach are proposed through rail under road as the preferred option at both Edithvale and Bonbeach.

Process

Exhibition of EES

The Environment Effects Statement (EES) for the Edithvale Bonbeach Level Crossing Project, together with the draft Planning Scheme Amendment, has been released for public comment for a period of 30 business days, from 19 March to 2 May 2018.

Details on the public exhibition process are provided in the EES exhibition public notice (PDF, 135.7 KB).

Online submissions are preferred and can be lodged via an online form at Engage Victoria

Inquiry

A joint Inquiry and Advisory Committee (IAC) has been appointed by the Minister for Planning under the Environment Effects Act 1978 and Planning and Environment Act 1987. Information on the IAC process and timetable for the hearings will be published as it becomes available at Engage Victoria.

Consultation plan

LXRA have prepared a communication and consultation plan for the EES, outlining the opportunities and approaches for its community engagement during the preparation of the EES.

The plan may be updated as required during the preparation of the EES. If the plan changes, the updated version will be posted on this page.

Scoping requirements

The Scoping Requirements set out the matters to be investigated and documented in the EES. Draft Scoping Requirements for this EES were on public exhibition between 14 August 2017 to 4 September 2017.

After considering public submissions on the Draft Scoping Requirements, the Minister for Planning issued final Scoping Requirements in September 2017.

Minister's Decision: EES Requested

On 5 May 2017 the Minister for Planning requested Level Crossing Removal Authority to prepare an Environmental Effects Statement (EES) under the Environment Effects Act 1978 to assess the potential environmental effects of the project:

More information

If you have any questions or feedback, please get in touch via the contact details below.

  • Proposed Edithvale and Bonbeach Level Crossing Removal Project:
    Level Crossing Removal Authority - LXRA
    ☎ Phone:1800 762 667
    ✉ Email: contact@levelcrossings.vic.gov.au

Panel or Committee

Background

The Minister for Planning will appoint an Inquiry and Advisory Committee (IAC) to consider the Environment Effects Statement, draft planning scheme amendments (PSA) affecting the Kingston Planning Scheme and public submissions associated with the Edithvale Bonbeach Level Crossing Removal Project in accordance with the approved Terms of Reference.

Terms of reference

The Terms of Reference will be available here.

Committee members

Further information will be available here.

Progress

Exhibition period and submissions

Submissions are invited between 19 March and 5.00pm on Wednesday 2 May 2018.

Make a submission

Directions hearing

A directions hearing will be held:

    Wednesday 9 May 2018 at 10.00am
    Patterson River Golf Club, The Fairway, Bonbeach

Public hearings

Public hearings will commence the week commencing 4 June 2018 at Patterson River Golf Club, The Fairway, Bonbeach. A hearing timetable will be issued following the directions hearing.

Report

After hearings have concluded, the IAC will submit its report in accordance with the Terms of Reference.

More information

If you have any questions or need further information, get in touch via the contact details below.

  • For information about the Inquiry and Advisory Committee process and submissions, please contact:
    Planning Panels Victoria
    ☎ Phone: (03) 8392 5121
    ✉ Email: planning.panels@delwp.vic.gov.au

Have your say

The Environment Effects Statement (EES) and draft Planning Scheme Amendment are currently available for pubic comment.

Status: Open

Edithvale & Bonbeach Level Crossing Removal

Have your say on the Edithvale & Bonbeach Level Crossing Removal Project

Submissions opens on

12.00am - Monday 19 March 2018

Submissions close on

5.00pm - Wednesday 02 May 2018

The Environment Effects Statement (EES) for the Edithvale Bonbeach Level Crossing Project, together with the draft Planning Scheme Amendment, has been released for public comment for a period of 30 business days, from 19 March to 2 May 2018.

Details on the public exhibition process are provided in the EES exhibition public notice (PDF, 135.7 KB) (PDF, 5.6 MB).

Online submissions are preferred and can be lodged via an online form at Engage Victoria.

Have your say

Documents

All supporting documents for this project can be found here.

Project documents

Minister's Reason for Decision:

Consultation Plan:

Scoping Requirements:

Public Notice:

Terms of Reference: