The Government Land Planning Service (GLPS) manages planning provisions relating to land owned by the Victorian Government.

This includes ensuring that appropriate planning provisions are in place on government land, correcting anomalies and updating planning provisions to accurately reflect planning use and development.

Sites considered under stream B require a planning scheme amendment/permit to be considered by the Government Land Standing Advisory Committee. The Advisory Committee collects submissions, facilitates a Hearing process and provides a report with recommendations on the planning proposal to the Minister for Planning.

Panel or Committee

The Government Land Standing Advisory Committee (GLSAC) was appointed in July 2015 to consider planning proposals for land owned, proposed to be owned in the future or to facilitate the delivery of priority projects by the Victorian Government.

Terms of reference

Committee members

  • Lester Townsend (Chair)
  • Mandy Elliott (Deputy Chair)
  • Lisa Kendal (Deputy Chair)
  • Trevor McCullough (Deputy Chair)
  • Annabel Paul (Deputy Chair)
  • Elissa Bell
  • Meredith Gibbs
  • Jonathan Halaliku
  • Prue Mansfield
  • Elizabeth McIntosh
  • Cazz Redding
  • Lynn Sweeney

Learn more about the members by reading their biographies (DOCX, 37.2 KB)

Process

Referral

The Minister for Planning refers sites in tranches for the Committee's consideration.

Exhibition

Timing: minimum 6 weeks.

The proposal for the site is placed on exhibition, including the relevant documentation and background reports. Submissions can be made during this period on Engage Victoria.

During Exhibition, the Committee may hold a Public Information Session to enable the general public to ask questions about the proposal and process.

Public Hearing

Timing: 4 weeks.

Once the Committee has received all the submissions, a Public Hearing is held to provide submitters with an opportunity to be heard. This occurs roughly 20 business days after the close of exhibition.

Report

Timing: 4 weeks.

The Committee submits its report to the Minister for Planning within 20 business days from the last day of the Public Hearing or the final date of any further submissions requested by the Committee during the Public Hearing. Reports are released at the discretion of the Minister for Planning. This usually happens once a decision has been made on the matter.

Make a submission on a specific referral and find out more about the Advisory Committee process: Engage Victoria

Find out more about the Government Land Planning Service process and recent decisions: Government Land Planning Service

More Information

If you have any questions or need further information, get in touch via the contact details below.

  • For information about the Government Land Planning Service process, please contact:
    Government Land Planning Service
    ☎ Phone: (03) 8392 5593
    ✉ Email: glp.service@delwp.vic.gov.au
  • For information about the Advisory Committee and how to make a submission, please contact:
    Planning Panels Victoria
    ☎ Phone: (03) 8392 5137
    ✉ Email: planning.panels@delwp.vic.gov.au

Have your say

Find out how to get involved and have your say on specific planning reviews

Status: Open

Government Land Standing Advisory Committee

Government Land Standing Advisory Committee

Matters are referred to the Government Land Standing Advisory Committee in tranches. To view the list of referrals and to make a submission on a particular tranche, please visit Engage Victoria.

Have your say

Documents

All documentation relating to this project can be found here.

Government land policies and guidelines and previous Committee reports