Waurn Ponds Train Stabling and Maintenance Facility
The Minister for Planning has referred the proposal to the Government Land Standing Advisory Committee (advisory committee) for advice and recommendations.
The Minister for Planning referred proposed Amendment GC104 to the Greater Geelong and Surf Coast Planning Schemes (amendment) to the Government Land Standing Advisory Committee (advisory committee) for advice and recommendations.
The amendment seeks to facilitate the Waurn Ponds Train Maintenance and Stabling Facility.
Read about the final outcome below.
Advisory Committee Report
The advisory committee recommended that the amendment be approved as exhibited, with changes as outlined in its report.
Ministers Decision
The Minister for Planning has approved the amendment as recommended by the advisory committee, with further changes.
The approved Amendment GC104 to the Greater Geelong and Surf Coast planning schemes was gazetted on 2 July 2020.
Information Pack
Proposal
Documents included in the information pack represent the proposed planning provision changes and associated background information exhibited as part of the advisory committee process. Please see the ‘Minister’s Decision’ (above) for the approved amendment, including changes to the exhibited proposal.
- Instruction Sheet (DOC, 69.0 KB)
- Explanatory Report (PDF, 446.3 KB)
- Waurn Ponds Train Maintenance and Stabling Facility Project Incorporated Document - June 2019 (PDF, 349.7 KB)
Note: In response to directions of the advisory committee, Appendix 1 to the incorporated document was corrected on 22 October 2019.
Greater Geelong Planning Scheme
- Clause 45.01 Public Acquisition Overlay (PDF, 882.8 KB)
- Schedule to Clause 45.01 Public Acquisition Overlay (DOCX, 32.5 KB)
- Public Acquisition Overlay map (PDF, 266.1 KB)
Note: In response to directions of the advisory committee, the Public Acquisition Overlay map was corrected on 16 October 2019.
- Clause 45.12 Specific Controls Overlay (PDF, 788.5 KB)
- Schedule to Clause 45.12 Specific Control Overlay (DOCX, 3.3 MB)
- Specific Controls Overlay map (PDF, 131.3 KB)
Note: In response to directions of the advisory committee, the Specific Controls Overlay map was corrected on 22 October 2019.
- Schedule to Clause 51.01 Specific Sites and Exclusions (DOCX, 3.1 MB)
- Schedule to Clause 72.01 Responsible Authority For this Planning Scheme (DOCX, 3.1 MB)
- Schedule to Clause 72.03 What Does this Planning Scheme Consist of? (DOCX, 3.3 MB)
- Schedule to Clause 72.04 Documents Incorporated in This Planning Scheme (DOCX, 3.1 MB)
Surf Coast Planning Scheme
- Clause 45.12 Specific Controls Overlay (DOCX, 23.9 KB)
- Schedule to Clause 45.12 Specific Control Overlay (DOCX, 3.3 MB)
- Specific Controls Overlay map (PDF, 393.6 KB)
Note: In response to directions of the advisory committee, the Specific Controls Overlay map was corrected on 22 October 2019.
- Schedule to Clause 51.01 Specific Sites and Exclusions (DOCX, 3.1 MB)
- Schedule to Clause 72.01 Responsible Authority For this Planning Scheme (DOCX, 3.1 MB)
- Schedule to Clause 72.03 What Does this Planning Scheme Consist of? (DOCX, 3.1 MB)
- Schedule to Clause 72.04 Documents Incorporated in this Planning Scheme (DOCX, 3.1 MB)
Background Reports
Note: In response to directions of the advisory committee, the Information Sheet was updated on 16 October 2019.
- Planning Report – AECOM, June 2019 (PDF, 1.6 MB)
- Planning Report – AECOM, June 2019 Appendix A (PDF, 798.7 KB)
- Ecological Assessment – AECOM June 2019 (PDF, 9.6 MB)
- Lighting Planning and Recommendations – AECOM June 2019 (PDF, 1.0 MB)
- Social Impact Assessment – Public Place, June 2019 (PDF, 2.2 MB)
- Stormwater Management Plan – AECOM, June 2019 (PDF, 10.0 MB)
Note: Rail Projects Victoria has advised that the stormwater management plan previously provided was incomplete. The complete version was uploaded on 9 December 2019.
- Transport Impact Assessment – onemilegrid, June 2019 (PDF, 2.7 MB)
- Agricultural Impact Assessment – Ag-Challenge Consulting Pty Ltd, June 2013 (PDF, 1.4 MB)
- Bushfire Assessment and Development Report – Terramatrix, June 2019 (PDF, 8.2 MB)
- Noise Assessment – AJM, June 2019 (PDF, 2.7 MB)
- Landscape and Visual Assessment – AECOM, June 2019 (PDF, 10.2 MB)
- Consultation Report – Rail Projects Victoria, June 2019 (PDF, 2.6 MB)
Site Selection Reports
Note: In response to directions of the advisory committee, the following reports relating to site selection for the project were made available on 16 October 2019.
Sites D I and J
- Sites D I and J Report - Appendix A - Depot Estimates Site I1 stage 1a (PDF, 14.8 KB)
- Sites D I and J Report - Appendix A - Depot Estimates Site I2 stage 1a (PDF, 85.5 KB)
- Sites D I and J Report - Appendix A - Depot Estimates Site J1 stage 1a (PDF, 14.8 KB)
- Sites D I and J Report - Appendix A - Depot Estimates Site J2 stage 1a (PDF, 15.6 KB)
- Sites D I and J Report - Appendix A - Depot Estimates Site I&J stage 1b (PDF, 14.7 KB)
- Sites D I and J Report - Appendix A - Depot Estimates Site I&J stage 2 (PDF, 15.6 KB)
- Sites D I and J Report - Appendix B - 4890-C-0700_P1 (PDF, 184.5 KB)
- Sites D I and J Report - Appendix B - 4890-C-0701_P1 (PDF, 184.5 KB)
- Sites D I and J Report - Appendix B - 4890-C-0702_P1 (PDF, 2.8 MB)
- Sites D I and J Report - Appendix B - 4890-C-0703_P1 (PDF, 3.0 MB)
- Sites D I and J Report - Appendix B - 4890-C-0704_P1 (PDF, 2.8 MB)
Site E
- Site E Report (PDF, 335.8 KB)
- Site E Report - Appendix 1 (PDF, 1.6 MB)
- Site E Report - Appendix 2 (PDF, 512.8 KB)
- Site E Report - Appendix 3 (PDF, 104.4 KB)
- Site E Report - Appendix 4 (PDF, 433.6 KB)
- Site E Report - Appendix 5 (PDF, 328.2 KB)
Site F
- Site F Report (PDF, 550.0 KB)
- Site F Report - Appendix 1 - Depot Estimates Site F Stage 1a (PDF, 36.2 KB)
- Site F Report - Appendix 1 - Depot Estimates Site F Stage 1b (PDF, 35.1 KB)
- Site F Report - Appendix 1 - Depot Estimates Site F Ultimate (PDF, 36.2 KB)
- Site F Report - Appendix 2 - 4890-C-0201_P1 (PDF, 1.9 MB)
- Site F Report - Appendix 2 - 4890-C-0202_P1 (PDF, 1.9 MB)
Site G
- Site G Report - 2010 (PDF, 10.6 MB)
- Site G Report - 2015 (PDF, 2.0 MB)
- Site G Report 2015 - Appendix 2 - stage 1a (PDF, 34.8 KB)
- Site G Report 2015 - Appendix 2 - stage 1b (PDF, 35.2 KB)
- Site G Report 2015 - Appendix 2 - ultimate (PDF, 36.0 KB)
- Site G Report 2015 - Appendix 3 - 4890_G0001_P1 (PDF, 494.0 KB)
- Site G Report 2015 - Appendix 4 - 4890-C-0001_P2 (PDF, 494.0 KB)
- Site G Report 2015 - Appendix 4 - 4890-C-0100_P2 (PDF, 1.7 MB)
Site X
- Site X Report (PDF, 1004.4 KB)
- Site X Report - Appendix 1 (PDF, 122.2 KB)
- Site X Report - Appendix 2 - 4890-C-0302_P1 (PDF, 2.1 MB)
- Site X Report - Appendix 2 - 4890-C-0402_P1 (PDF, 2.0 MB)
- Site X Report - Appendix 2 - 4890-C-0502_P1 (PDF, 2.1 MB)
- Site X Report - Appendix 2 - 4890-C-0602_P1 (PDF, 2.2 MB)
More Information
If you have any questions about this project, get in touch via the contact details below.
- Project process and timing:
Rail Projects Victoria
☎ Phone: 1800 105 105
✉ Email: regionalrailrevival@railprojects.vic.gov.au
- Advisory Committee process or timing:
Planning Panels Victoria
☎ Phone: (03) 8392 5121
✉ Email: planning.panels@delwp.vic.gov.au
- All other questions:
Government Land Planning Service
Department of Environment, Land, Water and Planning
☎ Phone: (03) 9637 8628
✉ Email: glp.service@delwp.vic.gov.au
Page last updated: 14/07/20