The Minister for Planning is the responsible authority for new planning permit applications for all energy generation facilities that are 1 megawatt or greater. This includes both renewable energy facilities and non-renewable energy facilities such as:

  • wind
  • solar
  • pumped hydro
  • gas
  • waste-to-energy

The Minister for Planning is also the responsible authority for new planning permit applications for utility installations. This includes utility installations that send or distribute electricity, such as powerlines, or that store electricity if the installed capacity is 1 megawatt or greater, such as battery storage.

Wind energy amendments

Amendment VC199 (gazetted 3 February 2022) changes the Victorian Planning Provisions and all planning schemes to align existing provisions with current policy, guidelines and legislation, delete redundant content and correct clerical errors. This includes changing the mandatory noise assessment requirement for an environmental audit report at clause 52.32-4 to require a verification report.

Amendment VC212 (gazetted 13 October 2021) changes the Victorian Planning Provisions and some planning schemes to support the ongoing operation of wind energy facilities and increases the amenity protections for nearby accommodation uses.

Amendment VC206 (gazetted 3 August 2021) changes the Victorian Planning Provisions and all planning schemes by modifying the particular provisions at clause 52.32 to remove the mandatory condition requirement for post construction noise assessment reports, clause 66.03 to make the Environmental Protection Authority a recommending referral authority for an application to amend a permit for a wind energy facility and updated clauses 19.01-2S and 52.32-6 to refer to current policy.

Amendment VC195 (gazetted 11 March 2021) changes the Victorian Planning Provisions and all planning schemes by modifying the particular provision at clause 52.32 (Wind energy facilities) to alter the exemptions for an application to amend a planning permit for a wind energy facility made under section 72 and 97 of the Planning and Environment Act 1987.

Amendment VC192 (gazetted 16 November 2020) changes the Victoria Planning Provisions and all planning schemes to make the Minister the responsible authority for all large energy generation facilities and utility installations.

Amendment VC160 (gazetted 24 January 2020) changes the Victoria Planning Provisions and all planning schemes by clarifying the mandatory noise assessment and mandatory conditions for wind energy facilities do not apply to applications to amend a planning permit where the changes will not alter the noise assessment of the wind energy facility.

Amendment VC161 (gazetted 17 September 2019) changes the Victoria Planning Provisions and all planning schemes to introduce new requirements for renewable energy facilities. The Minister for Planning is now the responsible authority for all new renewable energy facilities and utility installations that are 1 megawatt or greater, including battery storage.

Amendment VC159 (gazetted 8 August 2019) changes the Victoria Planning Provisions and all planning schemes to introduce and revise land use terms. This included amending the definition of ‘Utility installation’ to include transmit, distribute or store power, including battery storage.

Amendment VC157 (gazetted 15 March 2019) changes the Victoria Planning Provisions and all planning schemes so that a planning permit is required for a power line or substation required to connect an energy generation facility (including a wind farm) to the electricity network. This does not apply to generators that had planning approval prior to gazettal of the amendment.

Amendment VC141 (gazetted 21 November 2017) changes the Victorian Planning Provisions and all planning schemes by updating Clause 19.01 and amending Clause 52.32 to reflect changes proclaimed through the Planning and Building Legislation Amendment (Housing Affordability and Other Matters) Act 2017 in relation to an amendment to a planning permit for a windfarm. Clause 52.32-8 and 52.32-9 were added to specify that some amendments to called in planning permits for wind energy facilities are exempt from being referred to panel.

View previous wind energy amendments

Policy and planning guidelines

The policy and planning guidelines for development of wind energy facilities in Victoria help to inform planning decisions about proposals and set out:

  • a framework to provide a consistent and balanced approach to the assessment of wind energy facilities;
  • operational performance standards to inform the assessment and operation of wind energy facilities;
  • guidance as to how planning permit application requirements might be met.

The guidelines have been updated to address changes introduced by the amendments listed above.

Planning permit conditions

Model planning permit conditions for wind energy facilities have been developed to assist all parties involved in permit applications. They are provided in Appendix B of the Policy and planning guidelines for wind energy facilities in Victoria (DOCX, 122.3 KB).

The conditions are for guidance only and should be adapted depending on the individual circumstance of each wind energy proposal.

Guide to Victoria's planning system

Learn about the planning system in Victoria, including a complete guide to Using Victoria's Planning System (PDF, 2.8 MB)

Wind energy facilities in Victoria

At the start of 2020, Victoria had 26 operating wind energy facilities.

Information about these operating wind energy facilities, as well as information about other projects in Victoria that have lodged a planning permit application, have planning approval, or are under construction, can be found at the wind projects page.

Information about the steps the Victorian Government is taking to ensure the state makes the best use of its abundant wind resource as a renewable energy source can be found at the wind energy page.

VicPlan

Wind energy facilities in Victoria can be viewed on VicPlan, which is one of the Victorian Government's public GIS systems:

  1. Start VicPlan
  2. From the main toolbar, go to the ‘Map’ tab and click on the 'Layer Catalogue' button.
  3. Expand the 'Wind & Solar Farms' folders and select maps by ticking the check-box alongside each layer. Click OK.
  4. The selected layers will appear on the map and be listed in the layer control panel to the left of the map. You can turn these layers on and off by ticking the relevant check-box.

Pre-application service

DELWP provides a pre-application service to applicants. To arrange a meeting, please complete the Renewable Energy Pre-application Meeting Request form and send it to development.approvals@delwp.vic.gov.au

Native vegetation

Information relevant to native vegetation requirements can be found on the Native vegetation page.

Additional resources

Victorian government departments and agencies

Department of Environment, Land, Water and Planning:

Department of Jobs, Precincts and Regions:
Includes responsibility for agriculture, energy, resources, economic development, employment and innovation.

Sustainability Victoria:
A Victorian Government agency, established to accelerate sustainable resource supply and use across the Victorian economy. Their website includes information on a range of sustainability measures including wind and renewable energy.

Aboriginal Victoria:
Administers legislation that protects Aboriginal cultural heritage. Potential impacts of a wind energy facility on Aboriginal cultural values must be considered in the early planning stages of a development.

Useful publications and references

Greenhouse benefits

Information for calculating the greenhouse benefits of wind energy development, and other helpful links and resources are provided below.

A guide to calculating greenhouse benefits of wind energy facility proposals:

Birds and bats

DELWP is improving the regulation of wind farm impacts on birds and bats.

The aim is to ensure species at potential risk are protected by regulations that are clear, proportionate and effective.

The Victorian Brolga (Antigone rubicunda) is the first species DELWP is reviewing. DELWP is using new information about the impact of wind farms on this bird to update the ‘Interim Guidelines for the Assessment, Avoidance, Mitigation and Offsetting of Potential Wind Farm Impacts on the Victorian Brolga Population 2011’ (Interim Guidelines).

Submissions on the draft Brolga Assessment and Mitigation Standards closed late December 2020.

DELWP is now considering those submissions. For project updates, visit the Engage Victoria website.

Other species to be reviewed are being informed by two technical reports by the Arthur Rylah Institute. The first report developed an approach to determine the species at potential risk from the impacts of wind turbine collisions, at the state-wide population level.

The second report collated and analysed post-construction bird and bat mortality data collected by Victorian wind energy facilities.

Page last updated: 27/01/23